Baseline schedule
A baseline schedule was set-up during the pre-construction phase. Rakhi is responsible for weekly schedule updates, tracking progress and sharing project updates with the client. The construction phase of the project started in May 2021 comprising 13 phases with a contractual duration of 56 days for each phase. Every week, progress is marked against the baseline and the budgeted costs. “Despite the initial delay in the first three months, we have made remarkable progress on the project. The first phase took about 90 days to complete; whereas Phase 3 was finished in just 35 days, and we are now aiming to finish the upcoming phases in approximately the same time” says Rakhi. This means that the project is forecast to finish well in advance of the stipulated completion date.